Sewage Treatment AIN MANZOUL ROAD & RIVER – September 2018

– Total distance executed compromising excavation and all necessary works is: 1.3 Km
– Duration period for project implementation, Testing and Commissioning in spite of terrain difficulties in the RIVER: 48 Days
– 10 days on AIN MANZOUL Road compromising excavation + pipes installation and landfilling and remaining 38 days in river where a complete concrete structure with iron beams were implemented for pipes protection

Day 40 - 1-9-2018

River

Day 41 - 2-9-2018

River

Day 42 - 3-9-2018

River

Day 43 - 4-9-2018

River

Day 44 - 5-9-2018

River

Day 45 - 6-9-2018

Road

Day 46 - 13-9-2018

Road

Day 47 - 14-9-2018

Road

Day 48 - 15-9-2018

Road

Sewage Treatment AIN MANZOUL ROAD & RIVER – August 2018

– Total distance executed compromising excavation and all necessary works is: 1.3 Km
– Duration period for project implementation, Testing and Commissioning in spite of terrain difficulties in the RIVER: 48 Days
– 10 days on AIN MANZOUL Road compromising excavation + pipes installation and landfilling and remaining 38 days in river where a complete concrete structure with iron beams were implemented for pipes protection

Day 13 - 1-8-2018

River

Day 14 - 2-8-2018

River

Road

Day 15 - 3-8-2018

River

Road

Day 16 - 4-8-2018

River

Day 17 - 5-8-2018

River

Day 18 - 6-8-2018

River

Day 19 - 7-8-2018

River

Day 20 - 8-8-2018

River

Day 21 - 9-8-2018

River

Day 22 - 10-8-2018

River

Day 23 - 11-8-2018

River

Road

Day 24 - 12-8-2018

River

Road

Day 25 - 13-8-2018

River

Road

Day 26 - 14-8-2018

River

Road

Day 27 - 15-8-2018

River

Day 28 - 16-8-2018

River

Day 29 - 17-8-2018

River

Day 30 - 18-8-2018

River

Day 31 - 19-8-2018

River

Day 32 - 20-8-2018

Road

Day 33 - 23-8-2018

River

Day 34 - 24-8-2018

River

Day 1 - 18-7-2018

River

Day 36 - 27-8-2018

River

Day 37 - 28-8-2018

River

Day 38 - 29-8-2018

River

Day 39 - 30-8-2018

River

Sewage Treatment AIN MANZOUL ROAD & RIVER – July 2018

– Total distance executed compromising excavation and all necessary works is: 1.3 Km
– Duration period for project implementation, Testing and Commissioning in spite of terrain difficulties in the RIVER: 48 Days
– 10 days on AIN MANZOUL Road compromising excavation + pipes installation and landfilling and remaining 38 days in river where a complete concrete structure with iron beams were implemented for pipes protection

Day 1 - 18-7-2018

River

Road

Day 2 - 19-7-2018

River

Road

Day 3 - 20-7-2018

River

Road

Day 4 - 21-7-2018

River

Road

Day 5 - 23-7-2018

River

Road

Day 6 - 24-7-2018

River

Road

Day 7 - 24-7-2018

River

Road

Day 8 - 26-7-2018

River

Road

Day 9 - 27-7-2018

River

Road

Day 10 - 28-7-2018

River

Road

Day 11 - 30-7-2018

River

Road

Day 12 - 31-7-2018

River

Road

Sewage – Mtein Mchikha – April – May 2018

Day 1 - 24-4-2018

Day 2 - 25-4-2018

Day 3 - 26-4-2018

Day 4 - 27-4-2018

Day 5 - 28-4-2018

Day 6 - 29-4-2018

Day 7 - 30-4-2018

Day 8 - 1-5-2018

Day 9 - 2-5-2018

Day 10 - 3-5-2018

Day 11 - 4-5-2018

Day 12 - 5-5-2018

Day 13 - 8-5-2018

Day 14 - 9-05-2018

Day 15 - 10-05-2018

Day 16 - 11-5-2018

Day 17 - 12-5-2018

Day 18 - 14-5-2018

Day 19 - 15-5-2018

Asphalting Mtein road and New drainage network

Finally, after many years of demanding and seeking to rehabilitate and whitewash the main road from Bezpein to Mchicha and Almtien up to Bologna Square. The efforts of Mayor Zuhair Bou Nader at the Ministry of Works and during the tenure of Minister Venianos have been fruitful thanks to the implementation of this long-awaited project.