Sewage Treatment MTEIN – MCHIKHA Main road:

– Total distance executed compromising excavation and all necessary works is:
1.6 Km
– Duration period for project implementation, Testing and Commissioning:
24 Days

Day 20 - 7-9-2018

Day 21 - 8-9-2018

Day 22 - 10-9-2018

Day 23 - 11-9-2018

Day 24 - 12-9-2018